Construction Update

Week of Feb. 23, 2015

Alumni Hall
The delivery of modular units for Alumni Hall is almost complete. 138 units have been assembled to date. There are 32 units that remain to be delivered and assembled.

The brick and stone work for the exterior of Alumni Hall has begun on the west wing and will continue through end of March 2015. The north and east wing will follow.

Site Work
Dependent upon the weather, excavation will begin this week for telecommunication cabling. This work will begin between the new Farmhouse and Paton House and continue its way across the Administration roadway and then lead up towards the Townhouses. This will require a partial road closure but the contractors will maintain one active lane of traffic in this area at all times during this process. Flag persons will be positioned as needed to ensure safe passage at all times.

Athletics
Work on the athletics fields is weather dependent. The contractors are awaiting good weather to continue work in this area.

We have received the permit for the foundation for the Field House. We have begun working on the foundation, starting with erosion control.

The new Athletics Field House is still on schedule for completion for the fall 2015 semester. Due to the cold weather, there has been a delay in the schedule for the baseball and multi-purpose field. They are now projected to come online in April.

All work is weather dependent, we will promptly notify the community of any changes.

Construction Logistics Plan - Winter/Spring 2015 (pdf)