Construction Update

Week of April 20, 2015

Alumni Hall
Alumni HallThe brick and stone work on the west wing of Alumni Hall will be completed this week. Work on the north and east wing will follow. The scaffolding will be removed on the west wing once the work is completed and moved to north and east wings. The brick and stone work will be completed by the end of June.

The interior work on Alumni Hall continues. This work includes HVAC, electrical, and plumbing systems, and sheetrock installation for the non-modular areas such as the classroom spaces and lounge spaces on the first floor.

Residence Hall B
Excavation will continue this week for the foundation of Residence Hall B. Once the excavation is complete, the contractors will begin the footings and foundation work. Deluxe has begun production on the modular units for Residence Hall B. A total of 64 units have been completed to date.

Site Work
Installation of the light poles will be completed this week. The remaining areas are the Choate parking lot, and the sidewalks in front of Paton House.

Landscaping around the campus will commence this week, weather permitting.

The installation of the new data lines that will lead from the Kessel Student Center to Willcox Hall has begun. The data lines will run behind the Mortola Library, across the pedestrian pathway and staircase that connects parking lot T to parking lot Z next to the library as well as the entrance 2 roadway. This means that there will be minor disruptions to the pedestrian pathways and stairway that connects Parking lot T to the pathway by Mortola Library and Choate Pond. Please adhere to the alternative pathways around this area. This work is weather dependent. Updates will be provided should there be any changes in the schedule for this work.

Athletics
Work on the fields has begun. The light poles have been installed. This week they will begin installing the concrete dugout pads for the baseball field as well as the installation of the fence pole and curbs.

Work on the new Field House will continue this week with placing concrete at the building foundation. Please expect concreate delivery trucks by Parking lot F, which is located behind Lienhard Hall.

Athletics

All work is weather dependent, we will promptly notify the community of any changes.

Construction Logistics Plan - April 2015 (pdf)